Get your FREE quote — no obligation, all London areas   ✦   Call 07591 260 252   ✦   Get your FREE quote — no obligation, all London areas   ✦   Call 07591 260 252   ✦  
Project Guide · By TrustBuilt Projects · Updated · 6 min read

Bathroom Renovation Timeline: Week-by-Week (London 2026)

A bathroom mid-renovation with stripped-back plasterboard walls, a freestanding bath disconnected with exposed pipework, a stepladder and building materials scattered across the floor

Most London bathroom renovations take 2-5 weeks on site, depending on scope. A cosmetic refresh can be done in a week. A full refit with new layout, plumbing and tiling typically takes 3-5 weeks. Here's the week-by-week breakdown of what happens and why.

Three project sizes — three different timelines

Project typeSite timeTotal (incl. planning/lead time)
Cosmetic refresh (paint, fittings, fixtures swap)1-2 weeks3-4 weeks
Full refit (same layout, new suite + tiles)3-4 weeks6-8 weeks
Full reconfiguration (new layout, moved plumbing)4-5 weeks8-12 weeks
Wet room conversion or premium spec4-6 weeks10-14 weeks

Before site work — the lead-up (2-4 weeks)

What happens before the builder arrives on day 1:

  1. Survey and quote — site visit, measurements, written quote (1 week)
  2. Spec finalisation — choose suite (bath, shower, basin, WC), tiles, fittings, paint, lighting. This usually takes longer than people expect — 1-2 weeks if decisive, longer if not
  3. Order materials — most fittings have 1-3 week lead times. Premium tiles often longer (4-6 weeks for special order)
  4. Contract signing + deposit — typically 30-40% deposit to lock the date

Skip or rush these and the build itself runs late. Lock the spec before the builder arrives.

Site week-by-week (full refit, 3-4 weeks)

Week 1: Strip-out + first fix

Days 1-2: Strip out everything — old suite (bath, shower, basin, WC), tiles to the brickwork, old flooring, old extractor fan, dated towel rail. Existing pipework and electrical capped off where moving. Waste disposed of (skip or waste removal van).

Days 3-5: First-fix plumbing — new pipework runs for any moved fittings, new waste pipes if needed, new isolation valves on every fitting. First-fix electrical — cabling for shower, extractor fan, mirror, shaver socket, towel rail, any new lighting. If installing underfloor heating, the substrate is prepared and the heating elements laid this week.

Week 2: Building + waterproofing + plastering

Days 6-7: Any structural work — boxing in pipes, new stud walls if reconfiguring layout, fixing failed timberwork or sub-floor.

Days 8-9: Waterproofing — tanking membrane to wet areas (essential behind tiles in showers, full bathroom for wet rooms). Skipping this is the #1 cause of long-term water damage in bathrooms.

Days 10: Plastering — walls and ceiling made good ready for paint or tiles. Plaster needs 7-10 days to fully cure before tiling, so this is often scheduled at the end of week 2.

Week 3: Tiling + second fix

Days 11-14: Tiling — wall tiles first (working bottom up), then floor tiles. Sequence matters: tile to a level, grout next day, silicone after grouting cures. Quality tilers spend a lot of time on cut-tile detailing around fittings and corners.

Days 15-16: Second-fix plumbing — install the bath/shower tray, WC, basin, taps, shower mixer. Final connections to first-fix pipework. First water test.

Day 17: Second-fix electrical — fit the extractor fan, lights, switches, towel rail. Building Regs Part P notification for any new circuits.

Week 4: Finishing + snagging

Days 18-19: Decoration — paint ceiling, paint any non-tiled walls, paint or stain woodwork (window sills, door frames). Final coat of paint.

Days 20-21: Final fittings — mirror, towel rails, toilet roll holders, soap dishes, shower screens. Door and any internal door hardware. Sealing around bath and shower with silicone (silicone needs 24 hours to cure before use).

Days 22-23: Snagging — walkthrough with builder to identify any defects (paint missed, tile slightly proud, silicone needs re-doing, light not aligned). Builder fixes within 1-2 days.

Day 24: Final clean and handover.

Day-by-day for a small project (1-2 week refresh)

A bathroom refresh — keeping the existing layout, swapping the suite, painting, maybe re-tiling — runs much faster:

What extends the timeline

What you can do to keep things on schedule

Living with bathroom renovation

If you only have one bathroom in the house, expect 2-3 weeks without a working shower. Realistic options:

If you have a second bathroom or en-suite, life carries on relatively normally.

Frequently asked questions

Can a bathroom renovation be done in a week?

Yes for a simple refresh (paint, swap basin and toilet, replace shower screen, change towel rail). No for a full refit with new tiles and any plumbing moves — that's 3-4 weeks minimum.

Why do bathroom renovations always seem to run over?

Spec changes mid-project, material delays (especially on premium tiles and bespoke items), and discovering hidden problems during strip-out. The first two are preventable; the third requires contingency in your timeline (add 20-30%).

Does the bathroom need to be unusable the whole time?

Generally yes if it's a full refit. There's no way to use the toilet when it's been disconnected. Bath/shower availability depends on which phase you're in. Plan for 2-3 weeks of disruption for a full refit.

Should I be on-site every day during the renovation?

Not necessary if you trust your builder. Most homeowners are out at work during the day. Weekly walkthroughs to check progress and address questions are ideal. Daily oversight isn't needed (and slows the builder down).

What's the snagging period for a bathroom?

Typically 2-4 weeks after handover. You list any defects (tile not flush, paint touch-ups needed, silicone redo) and the builder returns to fix them in one visit. Retention payment (usually 5%) released after snags are signed off.

Related services

Bathroom Refurbishment

Full bathroom refits across London — from cosmetic refresh to luxury wet rooms.

Learn more →

Wet Room vs Traditional

Which makes sense for a London home?

Learn more →

Bathroom Cost Guide

Detailed cost ranges for London bathroom renovations.

Learn more →

Planning a bathroom renovation?

Free site visit. We'll measure, discuss spec, share a realistic timeline for your project, and quote in writing.

Book Free Visit →
中文