Get your FREE quote — no obligation, all London areas   ✦   Call 07591 260 252   ✦   Get your FREE quote — no obligation, all London areas   ✦   Call 07591 260 252   ✦  
Project Guide · By TrustBuilt Projects · Updated · 5 min read

How Long Does a House Extension Take in London? (2026 Timeline)

Two-storey rear house extension under construction on a UK suburban home, with scaffolding, exposed grey blockwork walls, timber framing and a steel support beam over the opening

Homeowners often ask 'how long will my extension take?' expecting a number like 'about 12 weeks'. The honest answer is more nuanced: site work is 10-22 weeks depending on type, but the full project from first call to keys is usually 6-9 months including planning, design, and Party Wall agreements. Here's the realistic timeline.

The five phases of a London extension

  1. Design and planning
  2. Party Wall agreements (if applicable)
  3. Pre-start (contractor procurement, drawings, finalising spec)
  4. Site work (the actual build)
  5. Snagging and handover

Site work — the bit people picture when they think 'extension build' — is usually only 40-50% of the total project duration. Front-end design and approvals often take just as long.

Phase 1: Design and planning (6-14 weeks)

Permitted development route (faster)

If your extension falls under permitted development rights — typical for single-storey rear extensions up to 6m deep on terraces — you don't need full planning permission. You may need prior approval for the larger PD route (extensions over 4m deep on terraces), which takes 6-8 weeks. Architectural drawings take 2-4 weeks.

Full planning permission route

Double-storey extensions, side extensions, and most extensions in conservation areas need full planning permission. Architectural drawings: 4-6 weeks. Planning application processing: 8-12 weeks (8 weeks is the statutory determination period). Allow more time if your borough is slow or your case is contentious. In total, plan for 12-18 weeks from instruction to consent.

Phase 2: Party Wall agreements (4-8 weeks)

If your extension affects shared walls with neighbours (very common in London terraces and semis), you must serve notice under the Party Wall Act 1996. The process:

  1. Serve formal notice on each adjoining owner (2 months' notice required before work starts on most issues)
  2. Neighbour responds within 14 days — can consent, dissent, or do nothing (which counts as dissent)
  3. If dissented, each party appoints a Party Wall Surveyor (you can share one 'Agreed Surveyor')
  4. Surveyor(s) produce a Party Wall Award documenting the work, condition of neighbour's property, and dispute mechanism

Typical timeline from first notice to a signed Award: 6-10 weeks. Skip this and the neighbour can obtain an injunction stopping the work mid-build.

Phase 3: Pre-start (2-4 weeks)

Even after planning and Party Wall are sorted, you need:

Phase 4: Site work — the build (10-22 weeks)

Typical London extension site timelines:

Extension typeSite time
Single-storey rear (3m × 5m)10-14 weeks
Side-return only10-14 weeks
Wrap-around (rear + side combined)14-18 weeks
Double-storey rear16-22 weeks
Glazed box / structural glass extension16-24 weeks

Inside the site work timeline (single-storey example)

WeeksActivity
Week 1-2Site setup, scaffolding, excavation
Week 3-4Foundations, drainage, sub-floor
Week 5-7Walls up, structural steels installed
Week 8-9Roof, glazing, weather-tight envelope
Week 10-11First fix — electrical, plumbing, plastering
Week 12Second fix — kitchen install, finishes, doors
Week 13-14Snagging, final clean, handover

Phase 5: Snagging and handover (1-3 weeks)

After the contractor declares 'practical completion', there's a snagging period — typically 2-4 weeks — where you note any defects (gaps in finishes, doors not closing properly, paint touch-ups needed). The contractor returns to fix snags. Final retention (typically 5% of contract value held back from final payment) is released once snags are signed off.

Total timeline — realistic

For a typical London single-storey rear extension going through full planning:

Permitted development route can shave 6-10 weeks off the front end. Larger projects (double-storey, wrap-around with planning) typically run 8-12 months end to end.

What can extend the timeline

Frequently asked questions

Can I do anything to speed up the timeline?

Yes. Start design early (before you've sold your current house if you're buying-to-renovate). Serve Party Wall notices as soon as you have permission. Order long-lead materials (bi-folds, custom kitchen) as early as the spec is locked. Choose a builder with capacity rather than the cheapest one that's 6 months booked-up.

Is there a 'fastest' London borough for planning?

Wandsworth and Bromley tend to be relatively quick (8-10 weeks for straightforward applications). Camden, RBKC, Westminster and Hackney often run 12-16+ weeks. Conservation area applications add 4-6 weeks anywhere.

What time of year is best to start an extension?

Spring (Mar-May) is ideal — site work runs through summer with good weather, and you're typically in by autumn. Avoid starting major external work in November-January if you can — wet weather slows everything.

Can I stay in the house during a 14-week extension?

Yes for most single-storey extensions. The original rear wall stays in place until 'break-through' late in the build (typically week 8-10), so the existing kitchen/living area remains usable. The break-through phase (1-2 weeks) is the most disruptive — dust, no kitchen, no rear access — and many clients move out briefly for it.

What happens if the builder runs over time?

Most contracts have a target completion date with extension provisions for legitimate delays (weather, agreed variations). Liquidated damages clauses (typically £200-500/week) penalise the builder for late completion. A good contract protects both sides — make sure yours has clear extension-of-time provisions, not just damages.

Related services

House Extension

We deliver every type of extension across London — single-storey through to double-storey wrap-arounds.

Learn more →

Extension Cost Factors

The 11 factors that drive London extension costs.

Learn more →

Permitted Development Rules

What you can build without full planning permission in London.

Learn more →

Glass Extension Cost Guide

What a glazed-box or glass extension really costs in London, and what drives the price.

Learn more →

Want a realistic timeline for your London extension?

Free site visit. We'll talk through likely planning route, lead times, and give a written quote with realistic dates.

Book Free Visit →
中文